La Grande By Al Ghafoor
Progress No. 23
2020-09-10
95% Construction Works Completed. La Grande by Al Ghafoor's Front, Back and Side Construction has almost completed! Development Image(s) have also been uploaded in this update. Inner Finishing Finalization is also going on... in Progress!




Progress No. 20
2019-03-20
20th March, 2019: La Grande by Al Ghafoor's Front Elevation's coloring work has been completed and project's internal works are now going on...



Progress No. 19
2019-01-05
5th January, 2019: La Grande by Al Ghafoor's Front Elevation's coloring works are still going on...
.jpeg)

Progress No. 18
2018-07-16
16th July, 2018: La Grande by Al Ghafoor's Front Elevation's coloring works are going on...




Progress No. 17
2018-04-21
21st April, 2018: La Grande by Al Ghafoor's Front Elevation's colouring work started...
.jpeg)


Progress No. 16
2018-02-15
15th February, 2018: La Grande by Al Ghafoor's Front & Back Elevation Image(s) has been uploaded in this update.




Progress No. 14
2017-07-05
5th July, 2017: Block lifters are lifting blocks to Typical 17 | Electrical works are going on from Typical 13 to 16.


Progress No. 13
2017-06-06
6th June, 2017: Shuttering work at columns typical 19 part 1 | Steel fixer has started work on slab typical 19 part 2 | Paint labors are working at typical 2 | Shuttering 2 fixing frames and casting at typical 6 | Safe mix labors are fixing pipe line for concrete | Company labor cutting lifting concrete scrap and taking part in casting scrap slab typical 19 part 1 | Block masons are doing block masonry at typical 15 | Plaster leveling concrete at slab typical 19 part 1 | Electricians are looking after of piping at slab typical 19 part 1 | Block lifter is lifting raiti to typical 15 | Paranch labors are binding paranch at back side.



Progress No. 12
2017-02-04
4th February, 2017: 15 Typical Shattering Work | 15 Typical Columns & Lift Shattering Work | Blocks Masonry 10th Typical Part - 1 | Plaster Work 5th & 6th Typical Part - 2...



Progress No. 11
2017-01-05
January 05, 2017: Structure works, inner Plaster and other Electrical and Plumbing works are going on...