Grande Homes by Al Ghafoor
Progress No. 14
2019-03-24
24th March, 2019: The building's exterior coloring work has almost been done. Now working on the finalization of internal finishing works...




Progress No. 13
2018-12-10
10th December, 2018: The building's exterior coloring works are going on...
.jpeg)


Progress No. 12
2018-07-19
19th July, 2018: The building's plaster and coloring works are going on...



Progress No. 11
2018-04-19
19th April, 2018: The building's structural and plaster works are going on...


Progress No. 9
2017-12-11
13th December, 2017: Grande Homes Building's Structure Almost Completed...




Progress No. 8
2017-09-20
20th September, 2017: The Building's Structure Development Works Are Going On Rapidly...




Progress No. 7
2017-07-01
1st July, 2017: Front Right Side Under Ground Tank and Basement Complete | Columns Opening Work.




Progress No. 6
2017-06-01
1st June, 2017: Back side front building 3rd floor complete | 4th floor electric work piping work and block masonry work is going on... | Right side foundation complete and opening columns work.




Progress No. 5
2017-03-10
10th March, 2017 > Front side's one part completed. | Ground Floor Slab: Pouring has been completed. | First Floor Columns and Slab (Ready for Monday). | Ground Floor's Block Masonry has been completed.


Progress No. 4
2017-02-07
7th February, 2017: Ground Floor Block Masonry Work Almost Completed and Basement Plaster Work Has Also Been Completed | Grande Homes Part 2 Back Side, Last Typical Columns Pouring Ready For Tomorrow | Grande Homes Part 1 Back Side Last Typical Slab Pouring Ready For Next Monday...


Progress No. 3
2017-01-15
January 15, 2017: Project's Basement completed, Structure work has now also been started successfully...




Upcoming Project
2016-03-06
Grande Homes by Al Ghafoor has been announced and is coming soon...
Project's online pre-booking has been started!
#GrandeHomesByAlGhafoor